  "reviewedAt": "2026-09-17",
  "references": [
    {
      "unit": "FUQING-5",
      "design": "HPR1000",
      "country": "CN",
      "status": "Operational",
      "net_mwe": 1075,
      "gross_mwe": 1161,
      "first_concrete_pris": "2015-05-07",
      "first_grid": "2020-11-27",
      "commercial_pris": "2021-01-30",
      "construction_to_grid_years": 5.561,
      "construction_to_commercial_years": 5.736,
      "operator": "CNNC Fujian Fuqing Nuclear Power Co., LTD",
      "supplier": "Nuclear Power Institute of China",
      "source_id": "pris-api-CN",
      "locator": "items[id=937]",
      "retrieved_cutoff": "2026-09-17",
      "evidence_class": "international_database_reported",
      "decision_class": "conditional_scenario",
      "note": "PRIS milestones preserved verbatim; operator milestone differences in milestone-crosschecks.json. No Swiss delivery inference.",
      "claim_id": "build-years-fuqing-5",
      "country_label": "China",
      "display_name": "Fuqing 5",
      "exact_years": 5.735797399041752
    },
    {
      "unit": "BARAKAH-1",
      "design": "APR-1400",
      "country": "AE",
      "status": "Operational",
      "net_mwe": 1337,
      "gross_mwe": 1417,
      "first_concrete_pris": "2012-07-19",
      "first_grid": "2020-08-19",
      "commercial_pris": "2021-04-01",
      "construction_to_grid_years": 8.085,
      "construction_to_commercial_years": 8.701,
      "operator": "Nawah Energy Company",
      "supplier": "Korea Electric Power Corporation",
      "source_id": "pris-api-AE",
      "locator": "items[id=1050]",
      "retrieved_cutoff": "2026-09-17",
      "evidence_class": "international_database_reported",
      "decision_class": "conditional_scenario",
      "note": "PRIS milestones preserved verbatim; operator milestone differences in milestone-crosschecks.json. No Swiss delivery inference.",
      "claim_id": "build-years-barakah-1",
      "country_label": "United Arab Emirates",
      "display_name": "Barakah 1",
      "exact_years": 8.700889801505818
    },
    {
      "unit": "TAISHAN-1",
      "design": "EPR-1750",
      "country": "CN",
      "status": "Operational",
      "net_mwe": 1660,
      "gross_mwe": 1750,
      "first_concrete_pris": "2009-11-18",
      "first_grid": "2018-06-29",
      "commercial_pris": "2018-12-13",
      "construction_to_grid_years": 8.611,
      "construction_to_commercial_years": 9.068,
      "operator": "Taishan Nuclear Power Joint Venture Company Limited",
      "supplier": "FRAMATOME",
      "source_id": "pris-api-CN",
      "locator": "items[id=918]",
      "retrieved_cutoff": "2026-09-17",
      "evidence_class": "international_database_reported",
      "decision_class": "conditional_scenario",
      "note": "PRIS milestones preserved verbatim; operator milestone differences in milestone-crosschecks.json. No Swiss delivery inference.",
      "claim_id": "build-years-taishan-1",
      "country_label": "China",
      "display_name": "Taishan 1",
      "exact_years": 9.067761806981519
    },
    {
      "unit": "SANMEN-1",
      "design": "AP-1000",
      "country": "CN",
      "status": "Operational",
      "net_mwe": 1157,
      "gross_mwe": 1251,
      "first_concrete_pris": "2009-04-19",
      "first_grid": "2018-06-30",
      "commercial_pris": "2018-09-21",
      "construction_to_grid_years": 9.197,
      "construction_to_commercial_years": 9.424,
      "operator": "SANMEN NUCLEAR POWER CO., LTD.",
      "supplier": "WESTINGHOUSE ELECTRIC CORPORATION / MITSUBISHI HEAVY INDUSTRIES, LTD.",
      "source_id": "pris-api-CN",
      "locator": "items[id=879]",
      "retrieved_cutoff": "2026-09-17",
      "evidence_class": "international_database_reported",
      "decision_class": "conditional_scenario",
      "note": "PRIS milestones preserved verbatim; operator milestone differences in milestone-crosschecks.json. No Swiss delivery inference.",
      "claim_id": "build-years-sanmen-1",
      "country_label": "China",
      "display_name": "Sanmen 1",
      "exact_years": 9.423682409308693
    },
    {
      "unit": "VOGTLE-3",
      "design": "AP-1000",
      "country": "US",
      "status": "Operational",
      "net_mwe": 1117,
      "gross_mwe": 1250,
      "first_concrete_pris": "2013-03-02",
      "first_grid": "2023-03-31",
      "commercial_pris": "2023-07-31",
      "construction_to_grid_years": 10.078,
      "construction_to_commercial_years": 10.412,
      "operator": "Southern Nuclear Operating Company, Inc.",
      "supplier": "WESTINGHOUSE ELECTRIC CORPORATION",
      "source_id": "pris-api-US",
      "locator": "items[id=1042]",
      "retrieved_cutoff": "2026-09-17",
      "evidence_class": "international_database_reported",
      "decision_class": "conditional_scenario",
      "note": "PRIS milestones preserved verbatim; operator milestone differences in milestone-crosschecks.json. No Swiss delivery inference.",
      "claim_id": "build-years-vogtle-3",
      "country_label": "United States",
      "display_name": "Vogtle 3",
      "exact_years": 10.412046543463381
    },
    {
      "unit": "OLKILUOTO-3",
      "design": "EPR",
      "country": "FI",
      "status": "Operational",
      "net_mwe": 1575,
      "gross_mwe": 1660,
      "first_concrete_pris": "2005-08-12",
      "first_grid": "2022-03-12",
      "commercial_pris": "2023-05-01",
      "construction_to_grid_years": 16.581,
      "construction_to_commercial_years": 17.717,
      "operator": "TEOLLISUUDEN VOIMA OYJ",
      "supplier": "FRAMATOME",
      "source_id": "pris-api-FI",
      "locator": "items[id=860]",
      "retrieved_cutoff": "2026-09-17",
      "evidence_class": "international_database_reported",
      "decision_class": "conditional_scenario",
      "note": "PRIS milestones preserved verbatim; operator milestone differences in milestone-crosschecks.json. No Swiss delivery inference.",
      "claim_id": "build-years-olkiluoto-3",
      "country_label": "Finland",
      "display_name": "Olkiluoto 3",
      "exact_years": 17.71663244353183
    }
  ],
  "schedules": [
    {
      "id": "accelerated_conditional",
      "preparation_start": 2026,
      "law_available": 2028,
      "general_licence_start": 2028,
      "general_licence_end": 2032,
      "construction_licence_start": 2030,
      "construction_licence_end": 2034,
      "first_concrete": 2034,
      "construction_to_grid_years": 7,
      "commissioning_years": 1,
      "commercial_year": 2042,
      "unit_count": 1,
      "note": "Strong overlap, mature unchanged reference, prepared site, timely referendum/appeals, reserved factory slots and financial close. Favourable case, not a guaranteed minimum.",
      "as_of": "2026-09-17",
      "evidence_class": "explicit_analyst_schedule_assumptions",
      "decision_class": "conditional_scenario",
      "net_mwe_options": [
        1100,
        1600
      ],
      "second_unit": "Optional replication only after first project evidence and separate site/grid/financing capacity; no automatic learning credit.",
      "full_fleet_8_units_by_2050_supported": false,
      "label": "Favourable case",
      "description": "Timely decisions, a prepared site and secured suppliers.",
      "grid_year": 2041,
      "claim_id": "delivery-accelerated-conditional"
    },
    {
      "id": "planning_case",
      "preparation_start": 2026,
      "law_available": 2028,
      "general_licence_start": 2029,
      "general_licence_end": 2035,
      "construction_licence_start": 2033,
      "construction_licence_end": 2037,
      "first_concrete": 2037,
      "construction_to_grid_years": 9,
      "commissioning_years": 1,
      "commercial_year": 2047,
      "unit_count": 1,
      "note": "Illustrative planning case with regulatory/design overlap; not a probabilistic P50 forecast.",
      "as_of": "2026-09-17",
      "evidence_class": "explicit_analyst_schedule_assumptions",
      "decision_class": "conditional_scenario",
      "net_mwe_options": [
        1100,
        1600
      ],
      "second_unit": "Optional replication only after first project evidence and separate site/grid/financing capacity; no automatic learning credit.",
      "full_fleet_8_units_by_2050_supported": false,
      "label": "Planning illustration",
      "description": "Longer assessment and construction, with some work in parallel.",
      "grid_year": 2046,
      "claim_id": "delivery-planning-case"
    },
    {
      "id": "delayed_case",
      "preparation_start": 2026,
      "law_available": 2031,
      "general_licence_start": 2032,
      "general_licence_end": 2039,
      "construction_licence_start": 2037,
      "construction_licence_end": 2041,
      "first_concrete": 2041,
      "construction_to_grid_years": 11,
      "commissioning_years": 1,
      "commercial_year": 2053,
      "unit_count": 1,
      "note": "Political/licensing delay plus difficult execution. Construction can be worse: the OL3 reference exceeds 17 years from concrete to commercial operation.",
      "as_of": "2026-09-17",
      "evidence_class": "explicit_analyst_schedule_assumptions",
      "decision_class": "conditional_scenario",
      "net_mwe_options": [
        1100,
        1600
      ],
      "second_unit": "Optional replication only after first project evidence and separate site/grid/financing capacity; no automatic learning credit.",
      "full_fleet_8_units_by_2050_supported": false,
      "label": "Delayed case",
      "description": "Legal or licensing delays, followed by difficult construction.",
      "grid_year": 2052,
      "claim_id": "delivery-delayed-case"
    }
  ],
  "bridge": {
    "as_of": "2026-09-17",
    "mean_2021_2025_twh": {
      "beznau-1": 2.7508000000000004,
      "beznau-2": 2.8074,
      "goesgen": 7.0122,
      "leibstadt": 8.6974
    },
    "beznau_combined_mean_twh": 5.5582,
    "goesgen_leibstadt_combined_mean_twh": 15.7096,
    "evidence_class": "historical_average_not_supply_guarantee",
    "decision_class": "conditional_scenario",
    "source_refs": [
      {
        "source_id": "nuclear-history-calculation",
        "locator": "2021–2025 plant-year generation"
      }
    ],
    "limitation": "Includes outages, including Gösgen2025. No assumption that past average persists through LTO. Retirement dates remain operator intentions and conditional scenarios in Swiss delivery table."
  },
  "retirement_intentions": {
    "beznau-1": 2033,
    "beznau-2": 2032
  },
  "claims": [
    {
      "id": "build-years-fuqing-5",
      "label": "Fuqing 5: construction to commercial operation",
      "value": 5.735797399041752,
      "unit": "years",
      "status": "calculated",
      "period": "2015-05-07 to 2021-01-30",
      "definition": "Elapsed time between the IAEA PRIS construction-start and commercial-operation dates.",
      "limitation": "Earlier planning and licensing are outside this interval. Selected examples span designs and jurisdictions, not a representative statistical sample. Olkiluoto’s operator uses a different regular-production milestone.",
      "sources": [
        "pris-api-CN",
        "nuclear-delivery-calculations"
      ],
      "formula": "(2021-01-30 − 2015-05-07) in calendar days / 365.25.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "build-years-barakah-1",
      "label": "Barakah 1: construction to commercial operation",
      "value": 8.700889801505818,
      "unit": "years",
      "status": "calculated",
      "period": "2012-07-19 to 2021-04-01",
      "definition": "Elapsed time between the IAEA PRIS construction-start and commercial-operation dates.",
      "limitation": "Earlier planning and licensing are outside this interval. Selected examples span designs and jurisdictions, not a representative statistical sample. Olkiluoto’s operator uses a different regular-production milestone.",
      "sources": [
        "pris-api-AE",
        "nuclear-delivery-calculations"
      ],
      "formula": "(2021-04-01 − 2012-07-19) in calendar days / 365.25.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "build-years-taishan-1",
      "label": "Taishan 1: construction to commercial operation",
      "value": 9.067761806981519,
      "unit": "years",
      "status": "calculated",
      "period": "2009-11-18 to 2018-12-13",
      "definition": "Elapsed time between the IAEA PRIS construction-start and commercial-operation dates.",
      "limitation": "Earlier planning and licensing are outside this interval. Selected examples span designs and jurisdictions, not a representative statistical sample. Olkiluoto’s operator uses a different regular-production milestone.",
      "sources": [
        "pris-api-CN",
        "nuclear-delivery-calculations"
      ],
      "formula": "(2018-12-13 − 2009-11-18) in calendar days / 365.25.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "build-years-sanmen-1",
      "label": "Sanmen 1: construction to commercial operation",
      "value": 9.423682409308693,
      "unit": "years",
      "status": "calculated",
      "period": "2009-04-19 to 2018-09-21",
      "definition": "Elapsed time between the IAEA PRIS construction-start and commercial-operation dates.",
      "limitation": "Earlier planning and licensing are outside this interval. Selected examples span designs and jurisdictions, not a representative statistical sample. Olkiluoto’s operator uses a different regular-production milestone.",
      "sources": [
        "pris-api-CN",
        "nuclear-delivery-calculations"
      ],
      "formula": "(2018-09-21 − 2009-04-19) in calendar days / 365.25.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "build-years-vogtle-3",
      "label": "Vogtle 3: construction to commercial operation",
      "value": 10.412046543463381,
      "unit": "years",
      "status": "calculated",
      "period": "2013-03-02 to 2023-07-31",
      "definition": "Elapsed time between the IAEA PRIS construction-start and commercial-operation dates.",
      "limitation": "Earlier planning and licensing are outside this interval. Selected examples span designs and jurisdictions, not a representative statistical sample. Olkiluoto’s operator uses a different regular-production milestone.",
      "sources": [
        "pris-api-US",
        "nuclear-delivery-calculations"
      ],
      "formula": "(2023-07-31 − 2013-03-02) in calendar days / 365.25.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "build-years-olkiluoto-3",
      "label": "Olkiluoto 3: construction to commercial operation",
      "value": 17.71663244353183,
      "unit": "years",
      "status": "calculated",
      "period": "2005-08-12 to 2023-05-01",
      "definition": "Elapsed time between the IAEA PRIS construction-start and commercial-operation dates.",
      "limitation": "Earlier planning and licensing are outside this interval. Selected examples span designs and jurisdictions, not a representative statistical sample. Olkiluoto’s operator uses a different regular-production milestone.",
      "sources": [
        "pris-api-FI",
        "nuclear-delivery-calculations"
      ],
      "formula": "(2023-05-01 − 2005-08-12) in calendar days / 365.25.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "delivery-accelerated-conditional",
      "label": "Favourable case: first commercial operation",
      "value": 2042,
      "unit": "year",
      "status": "scenario",
      "period": "Illustrative first Swiss project; preparation begins in 2026",
      "definition": "Analyst schedule combining assumed legal availability, overlapping preparation and approvals, construction and commissioning.",
      "limitation": "A conditional first-unit case, with no assigned probability. Site approval, supplier slots, finance and legal change remain dependencies. Greater delay or cancellation is possible.",
      "sources": [
        "nuclear-delivery-calculations"
      ],
      "formula": "2034 first concrete + 7 years to first grid + 1 commissioning year = 2042. All durations are assumptions.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "delivery-planning-case",
      "label": "Planning illustration: first commercial operation",
      "value": 2047,
      "unit": "year",
      "status": "scenario",
      "period": "Illustrative first Swiss project; preparation begins in 2026",
      "definition": "Analyst schedule combining assumed legal availability, overlapping preparation and approvals, construction and commissioning.",
      "limitation": "A conditional first-unit case, with no assigned probability. Site approval, supplier slots, finance and legal change remain dependencies. Greater delay or cancellation is possible.",
      "sources": [
        "nuclear-delivery-calculations"
      ],
      "formula": "2037 first concrete + 9 years to first grid + 1 commissioning year = 2047. All durations are assumptions.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "delivery-delayed-case",
      "label": "Delayed case: first commercial operation",
      "value": 2053,
      "unit": "year",
      "status": "scenario",
      "period": "Illustrative first Swiss project; preparation begins in 2026",
      "definition": "Analyst schedule combining assumed legal availability, overlapping preparation and approvals, construction and commissioning.",
      "limitation": "A conditional first-unit case, with no assigned probability. Site approval, supplier slots, finance and legal change remain dependencies. Greater delay or cancellation is possible.",
      "sources": [
        "nuclear-delivery-calculations"
      ],
      "formula": "2041 first concrete + 11 years to first grid + 1 commissioning year = 2053. All durations are assumptions.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "beznau-mean-2021-2025",
      "label": "Beznau’s average annual electricity",
      "value": 5.5582,
      "unit": "TWh/year",
      "status": "calculated",
      "period": "2021–2025",
      "definition": "Combined net output of Beznau 1 and 2, averaged over five years, including outages.",
      "limitation": "Historical annual energy sets the scale. Replacement supply must also meet winter and hourly needs; the average is not guaranteed future output.",
      "sources": [
        "nuclear-history-calculation",
        "nuclear-delivery-calculations"
      ],
      "formula": "Sum the ten plant-year net-generation values in GWh; divide by five years and by 1,000.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "beznau-2-retirement",
      "label": "Beznau 2: announced retirement year",
      "value": 2032,
      "unit": "year",
      "status": "scenario",
      "period": "Operator intention announced December 2024",
      "definition": "Axpo’s announced operating horizon, recorded in ENSI’s tenth national report, introduction.",
      "limitation": "An operator intention, distinct from a fixed statutory lifetime. Continued operation remains subject to safety requirements and the owner’s decision.",
      "sources": [
        "ensi-cns-2025"
      ],
      "formula": "Use the operator intention recorded by ENSI; no lifetime extrapolation.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "beznau-1-retirement",
      "label": "Beznau 1: announced retirement year",
      "value": 2033,
      "unit": "year",
      "status": "scenario",
      "period": "Operator intention announced December 2024",
      "definition": "Axpo’s announced operating horizon, recorded in ENSI’s tenth national report, introduction.",
      "limitation": "An operator intention, distinct from a fixed statutory lifetime. Continued operation remains subject to safety requirements and the owner’s decision.",
      "sources": [
        "ensi-cns-2025"
      ],
      "formula": "Use the operator intention recorded by ENSI; no lifetime extrapolation.",
      "reviewedAt": "2026-09-17"
    },
    {
      "id": "nuclear-referendum-expected",
      "label": "Expected vote on the new-build ban",
      "value": 2027,
      "unit": "year",
      "status": "scenario",
      "period": "DETEC position checked 17 September 2026",
      "definition": "DETEC expects the referendum vote in 2027 after parliamentary approval of repeal.",
      "limitation": "Expected timing and outcome remain conditional. Repeal would allow project applications; it would not approve a station.",
      "sources": [
        "uvek-nuclear-status"
      ],
      "formula": "Directly reproduce DETEC’s stated expected vote year; no probability assigned.",
      "reviewedAt": "2026-09-17"
    }
  ],
  "selection": "Six completed reference units span four designs and four countries, including different outcomes within AP1000 and EPR designs. This is an illustrative selection, not a global sample or estimate of Swiss completion odds.",
  "inputs": [
    {
      "path": "data/nuclear-delivery-2026-09-17/reference-units.json",
      "sha256": "7f9c1580abee9e5e3d422247a2326ab0f14182a6140022eb6f756c2c6c961bc9",
      "bytes": 17847
    },
    {
      "path": "data/nuclear-delivery-2026-09-17/delivery-scenarios.json",
      "sha256": "c8685bed3cfb2656db36caaf328ab082cff954e03f050d7bd92c33f3b94198cc",
      "bytes": 4356
    },
    {
      "path": "data/nuclear-delivery-2026-09-17/existing-fleet-bridge.json",
      "sha256": "3ddd0db7e10d75051f50e77ad14ad95fd8c8ee022dbf8d3a728f7782db4f79e8",
      "bytes": 693
    },
    {
      "path": "data/nuclear-delivery-2026-09-17/swiss-delivery-evidence.json",
      "sha256": "c3b114a1fe7a246015c6822fe0f41c5e5c88c649fced4340c816662b3e55f577",
      "bytes": 10342
    },
    {
      "path": "data/nuclear-delivery-2026-09-17/source-catalog.json",
      "sha256": "ca2ad93238035c3fe2341f9f3dad44a8aafd1492051a71b173b72cf552378516",
      "bytes": 153955
    }
  ],
  "recommendations": [
    "Begin owner-led assessment of mature large-reactor designs.",
    "Procure the Beznau replacement bridge independently of new nuclear.",
    "Keep SMRs as a conditional option until reference performance and executable offers support investment.",
    "Make further units depend on site, grid, supplier and financing capacity; do not assume a fleet delivery rate."
  ]
}