  "as_of": "2026-09-22",
  "whole_system_price_ready": false,
  "gaps": [
    {
      "id": "SG01",
      "question": "Which physical PV sites deliver the national capacity and winter yield?",
      "category": "public_data_and_modelling",
      "next_action": "Reconstruct finite roof, facade, agricultural, infrastructure and alpine categories geographically. Separate overlapping potential, already built capacity, consent, structural work and connection costs.",
      "reason_material": "Uniform cheap-roof pricing is not a national supply curve; the illustrative 120–140 GWp exceeds the approximately 110 GWp implied by one mixed-source potential diagnostic."
    },
    {
      "id": "SG02",
      "question": "What hourly solar output and storage/backup volume match the comparison demand?",
      "category": "public_data_and_modelling",
      "next_action": "Resolve energy units, time zone and the no-leap-day calendar of the verified municipal sample. Aggregate appropriate orientations and scenario weights, then rerun matched dispatch. The MWP archive is accessible; it is not an unavailable private input.",
      "reason_material": "Seasonal energy balance cannot choose dependable MW/MWh, and choosing storage size before dispatch biases the cost result."
    },
    {
      "id": "SG03",
      "question": "What network expenditure differs between matched portfolios?",
      "category": "public_model_extension_and_operator_data",
      "next_action": "Use geographical connection points and export limits. Separate shared asset renewal and demand growth from portfolio-specific reinforcement. Price obtaining the assumed demand or export flexibility.",
      "reason_material": "The published CHF 45–75 billion distribution totals and CHF 5.5 billion transmission plan are not a solar-only surcharge, and their scenario capacities are much smaller."
    },
    {
      "id": "SG04",
      "question": "What summer output earns revenue or displaces other real costs?",
      "category": "endogenous_model_output_and_commercial_uncertainty",
      "next_action": "Constrain domestic demand, charging and exports chronologically. Use common neighbour weather, price sensitivity and voluntary contracts. Distinguish financial receipts from national resource savings.",
      "reason_material": "Cheap PV and nuclear reverse their plant-only winter cost ranking at sufficiently valuable summer output; a fixed positive capture value at national overbuild scale is not secured."
    },
    {
      "id": "SG05",
      "question": "What are the actual EPC, battery warranty, roof-access and hydro-service offers?",
      "category": "accepted_commercial_unknown",
      "next_action": "Retain explicit price and risk scenarios until owners or suppliers disclose comparable offers. Do not repeat exhausted searches for private contract terms.",
      "reason_material": "Published budgets, surveys and finance allowances do not establish investability or owner participation."
    },
    {
      "id": "SG06",
      "question": "How do construction delay, financing and retirement affect the transition to 2050?",
      "category": "model_extension",
      "next_action": "Compare common year-by-year demand and plant commissioning, including interim imports/backup, nuclear delays, PV age cohorts, storage replacements and consistent terminal values.",
      "reason_material": "The plant comparison begins at commissioning; its construction carry does not include national bridge supply. The 25-year PV sensitivity has zero terminal salvage and is therefore separate from the 30-year base."
    },
    {
      "id": "SG07",
      "question": "Which source inconsistencies affect numerical interpretation?",
      "category": "explicit_source_uncertainty",
      "next_action": "Retain both facade winter-share interpretations; preserve rounded 98/99/about-100 TWh potential totals, ambiguous historical price/VAT basis, rounded Madrisa capacity and the superseded Grenchen schedule. Use documented scenarios rather than silent corrections.",
      "reason_material": "These change yield and cost comparisons; none justifies discarding the whole source or claiming false precision."
    },
    {
      "id": "SG08",
      "question": "Do adverse conditions change the preferred portfolio?",
      "category": "matched_reliability_and_economics_modelling",
      "next_action": "Test cold demand, dry hydro, prolonged low solar/wind, large reactor outages, constrained imports and construction slippage jointly. Price backup readiness, fuel, emissions and permission for actual operating patterns.",
      "reason_material": "Neither annual exports nor seasonal surpluses prove hourly adequacy; neither backup nor hydro flexibility is free."
    }
  ]
}