Independent research. Open evidence.
WattInfoEvidence for Swiss energy choices

A proposed path for Switzerland

More electric.
Ready for winter.

Electric heating and transport need more electricity. Winter brings the hardest supply test: heating rises while solar output falls.

We propose keeping Gösgen and Leibstadt while operation stays safe and economic for their owners, and developing two new reactors. Beznau’s planned retirement comes before new reactors in our schedule, so suppliers need separate winter supply to replace it. Hydro, useful renewables and further winter delivery remain part of the plan.

Demand and replacement evidence

Explore the 2050 programme

Production worth keeping

12.6 TWh

Switzerland’s reactors generated this much electricity from October 2024 to March 2025. Nuclear was the second-largest domestic source, after hydro.

Winter generation · BFE table 5

Why winter matters
Quick readAbout 1 min

Our choiceKeep productive reactors, build their successors and secure winter supply between them.

  1. Keep the winter contribution

    12.6 TWh

    Electricity from Swiss reactors in October 2024–March 2025. Nuclear was the second-largest domestic source, after hydro.

    Source and limits
  2. Two reactors leave winter supply to secure

    4.6 TWh

    Electricity still missing over the year with two new reactors in our demanding-weather 2050 case. Other winter supply is still needed.

    Same package with the two reactors removed and no replacement added: 13.3 TWh.

    Source and limits
  3. Replace Beznau before its successors arrive

    The announced retirement comes before our new-reactor dates. Electricity suppliers need a separate winter package for those earlier years.

    Source and limits

Keep in viewThe 2050 result uses 2016/17 weather, recorded October water and imports up to 2 GW. Our proposal depends on safety, approvals, credible delivery and viable owner contracts.

How much more electricity?

Electricity used by customers, before network losses.

Observed · 2024

57.5 TWh/year

What Switzerland used

The starting point for our electrification calculations.

Electricity consumption · BFE

Our scenario · 2050

94.2 TWh/year

What we plan for

More electric heating and transport, with efficiency gains and an allowance for data center growth.

Demand varies with weather. The data center allowance holds a published 2030 scenario constant through 2050.

Demand assumptions and calculation

See what changes electricity demand

Start here

How Swiss electricity works

Power, energy, winter supply and storage—explained with real Swiss data.

Read the guide

Follow the guide

Read in order, or choose a chapter

01

Swiss electricity, explained

Power, energy, winter supply and storage, with real Swiss data.

02

How much electricity will we need?

Electric heating and transport raise electricity demand. Our central sector scenario is about 93 TWh; the supply programme adds data center growth.

03

Keeping Switzerland powered through winter

Keep nuclear and hydro at the centre of winter supply. Add useful renewables, paid flexibility and contracted delivery for the remaining gaps.

04

What our dams can deliver

Prioritise Grimsel 4, Grimselsee and a viable Mattmark winter shift. Their different benefits depend on water, project delivery and paid owner services.

05

Where batteries and heat storage help

Use batteries for short gaps, store heat in suitable heating networks, and pay owners for useful services. Keep prolonged winter supply secure.

06

The case for keeping nuclear in the mix

Keep safe reactors, replace Beznau on time, and develop new nuclear with evidence from real builds and conditional Swiss delivery dates.

07

Compare the cost of dependable electricity

Prioritise viable nuclear extensions, develop complete new-build offers and pay for winter readiness. Generation prices cover only part of dependable supply.

08

Can more solar cover Switzerland’s winter?

Build economical solar with useful output and buyers. See what a much larger fleet costs, how summer sales change the comparison, and what still supplies winter nights.

09

Keep the lights on while new nuclear is built

Replace Beznau's output before new nuclear arrives, and buy emergency reserve separately. A timeline, purchasing roles and real Swiss reserve costs.

10

A supply plan for 2035, by day and by night

A concrete first package after Beznau, with solar, hydro, existing nuclear and realistic limits on what electric cars can contribute.

11

What Switzerland should build by 2050

New reactors reduce the winter supply gap. Our programme combines them with safe extensions, hydro and additional winter electricity.

12

A path to reliable Swiss electricity in 2050

Keep safe nuclear plants, develop their successors and build around winter needs. Our proposed direction, priorities and timetable.

Follow the evidence.
See the assumptions.

You should be able to check every number we use. Our source register links to original publications. Model results include their inputs, methods and limits.

We separate observations, calculations, policy targets and scenarios. When evidence is missing, we say so.

Open the source register